According to Russian Gazprom, its 42 bcmy Amur gas processing plant is 67.1% complete.
On the first two production trains, the construction, startup, and commissioning continue. At the third and fourth production trains, the installation of gas separation equipment has been completed. Meanwhile, in the fifth and sixth trains, the pipeline racks assembly and the installation of process equipment have begun.